Delay Claims in Data CentreConstruction: Part 1

Why they are different, why they are difficultand how they are proven By: Edward Foyle and Ahmed Elkordy   Introduction  Delay is a primary driver of cost overruns and disputes across all construction sectors. While standard conflicts over liquidated damages, extensions of time and prolongation costs remain central, data centre projects present a distinct risk profile. […]

Delay Claims in Data Centre Construction: Part 2

What to do when the delays occur, how to manage delays on the project and how to make a claim in respect of critical delay caused Part 1 of this article examined how and why data centre construction differs from traditional sectors, and considered common causes of delay and their impact on progress. This concluding […]